Professional Development
|
Research |
Continue to carry out research
Document research |
Research documented and published |
July 2011 |
|
|
Literacy Cycle Deployment |
Continue to work with lead teachers to develop literacy cycle within classrooms throughout the schools involved in the pilot |
Documented on the Manaiakalani Blog |
Continuously through until July 2011 |
|
Business Process |
Capture business processes |
Work closely with technical stream to assess requirement for documentation |
Requirements documented |
Continuously until July 2011 |
|
|
|
Document business processes identified |
Business processes documented |
|
|
Devices |
Requirements |
Identify and document requirements |
Device specification |
Completed |
|
|
Identify device that meets requirements |
Identify and test available devices |
Device Selection |
Completed August 2010 |
|
|
Procure |
Identify procurement partner |
Procurement partner |
September 2010 |
|
|
Deploy devices |
Develop deployment plan |
Plan signed off
|
November 2010 |
|
|
|
Carry out deployment |
All devices deployed |
|
|
|
Develop device management plan |
Develop business processes |
Business processes documented |
December 2010 |
|
|
Implement business processes |
Identify resources |
Resources established |
February 2011 |
|
|
|
Train resources |
Device management established |
|
|
Cloud solution |
Requirements |
Requirements for the solution components
Workshops with variety of stakeholders
|
Sign off |
Completed |
|
|
Build |
Developers convert requirements to new Google App for Education |
Sign off
Project Team |
Completed |
|
|
Test/Demonstrate |
Demonstration throughout Lead Teachers and involved schools |
Sign off by Lead Teachers |
Underway and completion by end September 2010 |
|
|
Training |
Develop training material |
Sign off by project team |
September 2010
|
|
|
SMS Integration |
Data integration with SMS-generated report data file for Assembly (Pt. England SMS)
Potentially, automated extraction from the SMS Web-based interface
Additional rules for provisioning and policy enforcement (focused on archiving and unenrollment
|
Sign off by project team |
September 2010
|
|
|
Parent Portal |
Parent portal interface
Cross-domain content migration on student move
Additional rules fine-tuning
|
Sign off by project team |
October 2010 |
|
WAN* |
Project Initiation |
Planning, Design, R&D |
Plan/Design complete |
2 months |
|
|
|
Proof of Concept |
Prototype network infrastructure
complete |
2 months |
|
|
Network Build |
Procurement |
Equipment procured |
1 month |
|
|
|
Configuration |
Configuration complete |
2 months |
|
|
|
Commissioning |
Commissioning complete |
2 months |
|
|
|
Backbone |
3 schools have backbone installed |
2 months |
|
|
|
Repeater installation |
45 Repeaters installed on HNZC houses |
2 months |
|
|
Handover |
Support |
|
3 months |
|
|
|
Documentation |
|
|
|
|
Review |
|
|
1 month |