Film Festival 2012

Student Survey

Warranty Issues

Insurance Claim

Pilot Project Approach

Methodology

The project will use the following approach:.


Phase

Approach

Initiation

 

Phase 1 (Project Initiation)

Approval of the Project Brief will mark the completion of the Initiation Phase.

Planning

 

 

Phase 2 (Project Execution Plan & Project Planning)

Literacy Cycle Rollout Plan

Research Method and Plan

Network Infrastructure Plan

Cloud Solution Plan

Device Procurement and Management Plan

Funding Plan

Execution

 

Stage 3 (Execute)

All deliverables signed off

Closure

 

Stage 4 (Project Closure)

Evaluation Review

Project Timing 

The below table outlines the high level planned completion dates for each phase of the project. As part of its planning, the project has developed an end to end schedule which incorporates the tasks and activities required to deliver its key milestones and deliverables. The table below provides a high level overview of key milestone/deliverable dates and estimated durations.

 

Workstream

Phase

Activity

Milestone

Timeframe

Professional Development

 

Research

Continue to carry out research

Document research

Research documented and published

July 2011

 

Literacy Cycle Deployment

Continue to work with lead teachers to develop literacy cycle within classrooms throughout the schools involved in the pilot

Documented on the Manaiakalani Blog

Continuously through until July 2011

Business Process

Capture business processes

Work closely with technical stream to assess requirement for documentation

Requirements documented

Continuously until July 2011

 

 

Document business processes identified

Business processes documented

 

Devices

Requirements

Identify and document requirements

Device specification

Completed

 

Identify device that meets requirements

Identify and test available devices

Device Selection

Completed August 2010

 

Procure

Identify procurement partner

Procurement partner

September 2010

 

Deploy devices

Develop deployment plan

Plan signed off

 

November 2010

 

 

Carry out deployment

All devices deployed

 

 

Develop device management plan

Develop business processes

Business processes documented

December 2010

 

Implement business processes

Identify resources

Resources established

February 2011

 

 

Train resources

Device management established

 

Cloud solution

Requirements

Requirements for the solution components

Workshops with variety of stakeholders

 

Sign off

Completed

 

Build

Developers convert requirements to new Google App for Education

Sign off

Project Team

Completed

 

Test/Demonstrate

Demonstration throughout Lead Teachers and involved schools

Sign off by Lead Teachers

Underway and completion by end September 2010

 

Training

Develop training material

Sign off by project team

September 2010

 

 

 

SMS Integration

Data integration with SMS-generated report data file for Assembly (Pt. England SMS)

Potentially, automated extraction from the SMS Web-based interface 

Additional rules for provisioning and policy enforcement (focused on archiving and unenrollment

 

Sign off by project team

September 2010

 

 

 

 

 

 

 

 

Parent Portal

Parent portal interface

Cross-domain content migration on student move

Additional rules fine-tuning

 

Sign off by project team

October 2010

WAN*

Project Initiation

Planning, Design, R&D

Plan/Design complete

2 months

 

 

Proof of Concept

Prototype network infrastructure

complete

2 months

 

Network Build

Procurement

Equipment procured

1 month

 

 

Configuration

Configuration complete

2 months

 

 

Commissioning

Commissioning complete

2 months

 

 

Backbone

3 schools have backbone installed

2 months

 

 

Repeater installation

45 Repeaters installed on HNZC houses

2 months

 

Handover

Support

 

3 months

 

 

Documentation

 

 

 

Review

 

 

1 month

*Project start dependent on releasing funding.

 

Dependencies

 

The project has identified key dependencies which have the potential to impact project delivery.  Upstream dependencies are documented in the table below

 

Dependency

Owner

Key Contact

Funding for the two stages of the pilot to be achieved

Pat Snedden

Rachel Hill

Specification and availability of devices

Russell Burt

Rachel Hill

Identification of schools to participate in pilot (school wireless capability readiness is a key dependency here)

 

Manaiakalani Cluster

Russell Burt

 

Identify students to participate in home and away

Manaiakalani Cluster

Dorothy Burt

Identify teachers and students to participate in school

Manaiakalani Cluster

Dorothy Burt

 

Constraints

The project has identified the following constraints which need to be considered by the project and which may impact on the project’s ability to deliver against its planned time frames: 

  • availability of funding for the full pilot as scoped 
  • Network capacity: 5Mb international, 10Mb national 
  • Location of state houses across the catchment 
  • MAC addresses limited to 1600 devices across the entire network 
  • Limitation of channels available in unlicensed spectrum constrains network design
 

Planning Assumptions

The project schedule developed is based on the information available at the time of creation. This means that the later stages of the project (particularly from the Development phase on) are less detailed than the earlier phases. The project’s level of confidence in the effort and duration estimations for the later phases is low.